Description | Establishes a general permit for the discharge of treated domestic sewage to surface waters provided, among other things, that the treatment works has a design discharge flow of less than or equal to 1,000 gallons per day on a monthly average. |
State Authority | Section 62.1-44.15 (10 ) of the Code of Virginia |
Federal Authority |
Section 402 of the Clean Water Act 40 Code of Federal Regulations, Parts 122, 123 and 124 |
Text of Regulation | Link to Virginia Administrative Code |
Goals of Regulation |
To protection public health and/or welfare with the least possible costs and intrusiveness to the citizens and businesses of the Commonwealth. To establish consistent procedures and requirements for the issuance of VPDES permits to discharge sewage from treatment works with design flows of 1,000 gallons per day or less in order to effectuate the proper and comprehensive protection of state waters. |
Meetings | See all meetings (24) relating to this chapter. |
Name / Title: | Peter Sherman |
Address: |
1111 East Main Street, Suite 1400 P.O. Box 1105 Richmond, VA 23218 |
Email Address: | peter.sherman@deq.virginia.gov |
Telephone: | (804)659-2666 FAX: ()- TDD: ()- |
Current Actions | ||
Action Title | Latest Stage | Status |
---|---|---|
CH110- 2026 Amendment and Reisuance of Existing Regulation
|
Proposed | Not yet submitted to Attorney General for certification. |
2024 40 CFR Part 136 Reference Update/Methods Update Rule
|
Final | Stage complete. Becomes effective on 12/18/2024. |
Past Actions | ||
Action Title | Latest Stage | Status |
---|---|---|
Final Exempt CH 110 Changes in Response to 2022 Board Bill
|
Final | Stage complete. This regulation became effective on 11/09/2022. |
2021 Amendment and Reissuance of the Existing Regulation
|
Final | Stage complete. This regulation became effective on 08/02/2021. |
Amend and Reissue the General Permit Regulation
|
Final | Stage complete. This regulation became effective on 08/02/2016. |
Amend and Reissue the General Permit Regulation
|
Final | Stage complete. This regulation became effective on 08/02/2011. |
Amendment of VPDES General Permit for Sewage Discharges Equal to or Greater than 1,000 Gallons Per Day
|
Final | Stage complete. This regulation became effective on 08/01/2001. |
Virginia Pollutant Discharge Elimination System General Permit for Sewage Discharges Equal to or Greater than 1,000 Gallons Per Day
|
Final | Stage complete. This regulation became effective on 08/01/2001. |
Withdrawn Actions | ||
Action Title | Latest Stage | Status |
---|---|---|
Reissuance of VPDES General Permit for Sewage Discharges Less Than or Equal to 1,000 Gallons Per Day
|
Final | Stage withdrawn on 08/23/2007 before submission to the Registrar. |