7/31/08  2:43 pm
Commenter: Diana Parker

DEQ Regulations for Treatment of Sewage Sludge in Virginia
 

As a member of Virginia Citizens for Protection from Sewage Sludge, i recommend the following: 

 
           1.    Chemical Analysis for the EPA Priority Pollutants as well as for the
               Biological Toxinsincluding and not limited to endotoxins, fecal coliform, etc.
2.  Five (5) mile buffer from habitat.
 
3.  Once sign is posted, citizens have fifteen business days before biosolids   
     applications begin.
 
4.  All signs posted should be the same perimeters as the re-zoning notice signs (4 x  
     8), and information on sign is visible from a distance of at least 20 ft. They must   
     be placed vertically to the roadway, straight up and down with no slant.
 
5.  All signs must have the name and phone number of the agency  or company   
     that has the authority to lift, modify or abate any and all biosolids applications.
 
6.  Make regulation that you must have proof of receipt for notification to citizens      
     adjacent to land applications and to those citizens within 1,000 ft of the land to    
     be applied.
 
7.  Biosolids applications can only be delivered and applied during business 
     daylight hours.
 
8.  Any damage to infrastructure or spillage caused by biosolids truck traffic should
     be paid by the haulers, spreaders and the recipients of the said treated sewage
     sludge and not the taxpayer.
 
9.  All land applications of biosolids must be recorded on each land deed. (impact
     on family)
 
10. Monies placed in escrow by both land owners and sludge companies to ensure 
      financial responsibility with direct proportion to the acreage to be applied.
 
11. Penalties imposed immediately upon violations. (License revoked, suspended, 
      etc., impound truck or trucks, pull permit, etc.).
 
12. Cleanup of roadways, etc. should be removed and deposited back on the truck or
      on the designated field ready for application.
 
13. Testing of soil semi-annually to ensure proper pH and that heavy metals remain
      bound in soil.
 
14. Field storage of biosolids should be covered at all times and stored no longer than
      20 days.
 
15. Field testing of all biosolids not applied within twenty-four hours for pH, and
      biological pathogens including fecal coliform.
 
16. When land applied, biosolids should be immediately incorporated into the soil.
 
17. When storing biosolids, retesting should be done, based on the fact that you are
      no longer dealing with the original contaminants or pathogens. It should be      
      considered a completely new source in itself. The retesting requirements  
      should be the same as the regulations for biosolids before land applied.  