Virginia Regulatory Town Hall

Final Text

highlight

Action:
Amendments Mandated by Chapter 368 of the 2017 Acts of Assembly
Stage: Final
 
9VAC15-70-10

9VAC15-70-10. Definitions.

The following words and terms when used in this chapter shall have the following meanings unless the context clearly indicates otherwise:

"Applicant" means the owner or operator who submits an application to the department for a permit by rule pursuant to this chapter.

"Archive search" means a search of DHR's cultural resource inventory for the presence of previously recorded archaeological sites and for architectural structures and districts.

"Coastal Avian Protection Zones" or "CAPZ" means the areas designated on the map of "Coastal Avian Protection Zones" generated on the department's Coastal GEMS geospatial data system (9VAC15-70-120 C 1).

"Combustion energy project," or "project" means a small renewable energy project that:

1. Is an electrical generation facility with a rated capacity not exceeding 20 megawatts that generates electricity only from biomass, energy from waste, or municipal solid waste; and

2. Utilizes a fuel or feedstock that is addressed as a regulated solid waste by 9VAC20-81, 9VAC20-60 9VAC20-60, 9VAC20-81, or 9VAC20-120; is defined as biomass pursuant to § 10.1-1308.1 of the Code of Virginia; or both.

"Department" means the Department of Environmental Quality, its director, or the director's designee.

"DCR" means the Department of Conservation and Recreation.

"DGIF" means the Department of Game and Inland Fisheries.

"DHR" means the Department of Historic Resources.

"Disturbance zone" means the area within the site directly impacted by construction and operation of the combustion energy project.

"Historic resource" means any prehistoric or historic district, site, building, structure, object, or cultural landscape that is included or meets the criteria necessary for inclusion in the Virginia Landmarks Register pursuant to the authorities of § 10.1-2205 of the Code of Virginia and in accordance with 17VAC5-30-40 through 17VAC5-30-70.

"Interconnection point" means the point or points where the combustion energy project connects to a project substation for transmission to the electrical grid.

"Natural heritage resource" means the habitat of rare, threatened, or endangered plant and animal species, rare or state significant natural communities or geologic sites, and similar features of scientific interest benefiting the welfare of the citizens of the Commonwealth.

"Operator" means the person responsible for the overall operation and management of a combustion energy project.

"Owner" means the person who owns all or a portion of a combustion energy project.

"Parasitic load" means the maximum amount of electricity (in megawatts or kilowatts) a combustion energy project uses to run its electricity-producing processes while operating at the rated capacity.

"Parking lot" means an improved area, usually divided into individual spaces and covered with pavement or gravel, intended for the parking of motor vehicles.

"Permit by rule" means provisions of this chapter stating that a project or activity is deemed to have a permit if it meets the requirements of the provision.

"Person" means any individual, partnership, firm, association, joint venture, public or private corporation, trust, estate, commission, board, public or private institution, utility, cooperative, county, city, town, or other political subdivision of the Commonwealth, any interstate body, or any other legal entity.

"Preconstruction" means any time prior to commencing land-clearing operations necessary for the installation of energy-generating structures at the combustion energy project.

"Rated capacity" means the maximum designed electrical generation capacity (in megawatts or kilowatts) of a combustion energy project, minus the parasitic load; sometimes known as "net capacity."

"Site" means the area encompassed by the combustion energy project, plus appurtenant structures and facilities such as fuel processing, delivery, storage, and associated conveyance equipment areas if they (i) are contiguous and (ii) primarily exist to supply fuel for the generation of electricity at that project, to the extent that these areas are under common ownership or operating control by the owner or operator of the combustion energy project.

"Small renewable energy project" means (i) an electrical generation facility with a rated capacity not exceeding 100 150 megawatts that generates electricity only from sunlight, or wind,; (ii) an electrical generation facility with a rated capacity not exceeding 100 megawatts that generates electricity only from falling water, wave motion, tides, or geothermal power,; or (ii) (iii) an electrical generation facility with a rated capacity not exceeding 20 megawatts that generates electricity only from biomass, energy from waste, or municipal solid waste.

"T&E," "state threatened or endangered species," or "state-listed species" means any wildlife species designated as a Virginia endangered or threatened species by DGIF pursuant to § 29.1-563-570 §§ 29.1-563 through 29.1-570 of the Code of Virginia and 4VAC15-20-130.

"VLR" means the Virginia Landmarks Register (9VAC15-70-120 B 1).

"VLR-eligible" means those historic resources that meet the criteria necessary for inclusion on the VLR pursuant to 17VAC5-30-40 through 17VAC5-30-70 but are not listed in the VLR.

"VLR-listed" means those historic resources that have been listed in the VLR in accordance with the criteria of 17VAC5-30-40 through 17VAC5-30-70.

"Wildlife" means wild animals; except, however, that T&E insect species shall only be addressed as part of natural heritage resources and shall not be considered T&E wildlife.

9VAC15-70-30

Part II
Permit by Rule Provisions for Combustion Energy Projects with Rated Capacity Greater Than Five Megawatts and Not Otherwise Meeting Criteria for Part III

9VAC15-70-30. Application.

A. The owner or operator of a combustion energy project with a rated capacity greater than five megawatts, provided that the project does not otherwise meet the criteria for Part III (9VAC15-70-130) of this chapter, shall submit to the department a complete application in which he satisfactorily accomplishes all of the following:

1. In accordance with § 10.1-1197.6 B 1 of the Code of Virginia, and as early in the project development process as practicable, furnishes to the department a notice of intent, to be published in the Virginia Register of Regulations, that he intends to submit the necessary documentation for a permit by rule for a small renewable energy project;

2. In accordance with § 10.1-1197.6 B 2 of the Code of Virginia, furnishes to the department a certification by the governing body of the locality or localities wherein the small renewable energy project will be located that the project complies with all applicable land use ordinances;

3. In accordance with § 10.1-1197.6 B 3 of the Code of Virginia, furnishes to the department copies of all interconnection studies undertaken by the regional transmission organization or transmission owner, or both, on behalf of the small renewable energy project;

4. In accordance with § 10.1-1197.6 B 4 of the Code of Virginia, furnishes to the department a copy of the final interconnection agreement between the small renewable energy project and the regional transmission organization or transmission owner indicating that the connection of the small renewable energy project will not cause a reliability problem for the system. If the final agreement is not available, the most recent interconnection study shall be sufficient for the purposes of this section. When a final interconnection agreement is complete, it shall be provided to the department. The department shall forward a copy of the agreement or study to the State Corporation Commission;

5. In accordance with § 10.1-1197.6 B 5 of the Code of Virginia, furnishes to the department a certification signed by a professional engineer licensed in Virginia that the maximum generation capacity of the combustion energy project, as designed, does not exceed 20 megawatts;

6. In accordance with § 10.1-1197.6 B 6 of the Code of Virginia, furnishes to the department an analysis of potential environmental impacts of the small renewable energy project's operations on attainment of national ambient air quality standards;

7. In accordance with § 10.1-1197.6 B 7 of the Code of Virginia, furnishes to the department, where relevant, an analysis of the beneficial and adverse impacts of the proposed project on natural resources. The owner or operator shall perform the analyses prescribed in 9VAC15-70-40. For wildlife, that analysis shall be based on information on the presence, activity, and migratory behavior of wildlife to be collected at the site for a period of time dictated by the site conditions and biology of the wildlife being studied, not exceeding 12 months;

8. In accordance with § 10.1-1197.6 B 8 of the Code of Virginia, furnishes to the department a mitigation plan pursuant to 9VAC15-70-70 that details reasonable actions to be taken by the owner or operator to avoid, minimize, or otherwise mitigate such impacts, and to measure the efficacy of those actions; provided, however, that the provisions of this subdivision shall only be required if the department determines pursuant to 9VAC15-70-50 that the information collected pursuant to § 10.1-1197.6 B 7 of the Code of Virginia and 9VAC15-70-40 indicates that significant adverse impacts to wildlife or historic resources are likely;

9. In accordance with § 10.1-1197.6 B 9 of the Code of Virginia, furnishes to the department a certification signed by a professional engineer licensed in Virginia that the project is designed in accordance with 9VAC15-70-80;

10. In accordance with § 10.1-1197.6 B 10 of the Code of Virginia, furnishes to the department an operating plan describing how any standards established in this chapter applicable to the permit by rule will be achieved;

11. In accordance with § 10.1-1197.6 B 11 of the Code of Virginia, furnishes to the department a detailed site plan meeting the requirements of 9VAC15-70-70;

12. In accordance with § 10.1-1197.6 B 12 of the Code of Virginia, furnishes to the department a certification signed by the applicant that the combustion energy project has applied for or obtained all necessary environmental permits;

13. In accordance with § 10.1-1197.6 H and I of the Code of Virginia, furnishes to the department a certification signed by the applicant that the small combustion energy project is being proposed, developed, constructed, or purchased by a person that is not a utility regulated pursuant to Title 56 of the Code of Virginia or provides certification that (i) the project's costs are not recovered from Virginia jurisdictional customers under base rates, a fuel factor charge, or a rate adjustment clause, or (ii) the applicant is a utility aggregation cooperative formed under Article 2 (§ 56-231.38 et seq.) of Chapter 9.1 of Title 56 of the Code of Virginia.

14. Prior to authorization of the project and in accordance with §§ 10.1-1197.6 B 13 and 10.1-1197.6 B 14 of the Code of Virginia, conducts a 30-day public review and comment period and holds a public meeting pursuant to 9VAC15-70-90. The public meeting shall be held in the locality or, if the project is located in more than one locality, in a place proximate to the location of the proposed project. Following the public meeting and public comment period, the applicant shall prepare a report summarizing the issues raised by the public and include any written comments received and the applicant's response to those comments. The report shall be provided to the department as part of this application; and

14. 15. In accordance with 9VAC15-70-110, furnishes to the department the appropriate fee.

B. Within 90 days of receiving all of the required documents and fees listed in subsection A of this section, the department shall determine, after consultation with other agencies in the Secretariat of Natural Resources, whether the application is complete and whether it adequately meets the requirements of this chapter, pursuant to § 10.1-1197.7 A of the Code of Virginia.

1. If the department determines that the application meets the requirements of this chapter, then the department shall notify the applicant in writing that he is authorized to construct and operate a combustion energy project pursuant to this chapter.

2. If the department determines that the application does not meet the requirements of this chapter, then the department shall notify the applicant in writing and specify the deficiencies.

3. If the applicant chooses to correct deficiencies in a previously submitted application, the department shall follow the procedures of this subsection and notify the applicant whether the revised application meets the requirements of this chapter within 60 days of receiving the revised application.

4. Any case decision by the department pursuant to this subsection shall be subject to the process and appeal provisions of the Administrative Process Act (§ 2.2-4000 et seq. of the Code of Virginia).