Virginia Regulatory Town Hall

Proposed Text

highlight

Action:
2024 Reissue and amend, as necessary, the Virginia Pollution ...
Stage: Proposed
 
9VAC25-192-10 Definitions

The following words and terms when used in this chapter shall have the meanings defined in the State Water Control Law (§ 62.1-44.2 et seq. of the Code of Virginia) and the Virginia Pollution Abatement (VPA) Permit Regulation (9VAC25-32) unless the context clearly indicates otherwise, except that for the purposes of this chapter:

"300 animal units" means 300,000 pounds of live animal weight, or the following numbers and types of animals:

a. 300 slaughter and feeder cattle;

b. 200 mature dairy cattle (whether milked or dry cows);

c. 750 swine each weighing over 25 kilograms (approximately 55 pounds);

d. 150 horses;

e. 3,000 sheep or lambs;

f. 16,500 turkeys;

g. 30,000 laying hens or broilers.

"Agricultural stormwater discharge" means a precipitation-related discharge of manure, litter, or process wastewater that has been applied on land areas under the control of an animal feeding operation or under the control of an animal waste end-user in accordance with a nutrient management plan approved by the Virginia Department of Conservation and Recreation and in accordance with site specific nutrient management practices that ensure appropriate agricultural land utilization of the nutrients in the manure, litter, or process wastewater.

"Animal feeding operation" means a lot or facility, together with any associated treatment works, where both of the following conditions are met:

1. Animals have been, are, or will be stabled or confined and fed or maintained for a total of 45 days or more in any 12-month period; and

2. Crops, vegetation, forage growth, or post-harvest residues are not sustained in the normal growing season over any portion of the operation of the lot or facility.

Two or more animal feeding operations under common ownership are a single animal feeding operation for the purposes of determining the number of animals at an operation, if they adjoin each other, or if they use a common area or system for the disposal of wastes liquid waste.

"Animal waste" means liquid, semi-solid, and solid animal manure and process wastewater, compost, or sludges associated with animal feeding operations including the final treated wastes generated by a digester or other manure treatment technologies.

"Animal waste end-user" or "end-user" means any recipient of transferred animal waste who stores or who utilizes the waste as fertilizer, fuel, feedstock, livestock feed, or other beneficial use for an operation under his the recipient's control.

"Animal waste fact sheet" means the document that details the requirements regarding utilization, storage, and management of animal waste by end-users. The fact sheet is approved by the department.

"Beneficial use" means a use that is of benefit as a substitute for natural or commercial products and does not contribute to adverse effects on health or environment.

"Board" means the State Water Control Board. When used outside the context of the promulgation of regulations, including regulations to establish general permits, "board" means the Department of Environmental Quality.

"Confined animal feeding operation," for the purposes of this regulation, has means the same meaning as an "animal feeding operation."

"Department" means the Department of Environmental Quality.

"Director" means the Director of the Virginia Department of Environmental Quality, or his designee an authorized representative.

"General permit" means this chapter.

"Land application" means the distribution of animal waste by spreading or spraying on the surface of the land, injecting below the surface of the land, or incorporating into the soil with a uniform application rate for the purpose of fertilizing crops or vegetation or conditioning the soil. The fields or sites used for the land application of animal waste in accordance with this chapter are not considered to be treatment works. Deposition of animal waste by an animal is not land application.

"Local government ordinance form" means a notification from the governing body of the county, city, or town where the animal feeding operation is located that the animal feeding operation is consistent with all ordinances adopted pursuant to Chapter 22 (§ 15.2-2200 et seq.) of Title 15.2 of the Code of Virginia.

"Nutrient management plan" or "NMP" means a plan developed or approved by the Department of Conservation and Recreation that requires proper storage, treatment, and management of animal waste and limits accumulation of excess nutrients in soils and leaching or discharge of nutrients into state waters; except that for an animal waste end-user who is not covered under the this general permit, the requirements of 9VAC25-192-90 constitute the NMP.

"Organic source" means any nutrient source including, but not limited to, manures, biosolids, compost, and waste or sludges from animals, humans, or industrial processes, but for the purposes of this regulation it excludes waste from wildlife.

"Permittee" means the owner or operator of an animal feeding operation or animal waste end-user whose animal waste management activities are covered under this general permit.

"Seasonal high water table" means that portion of the soil profile where a color change has occurred in the soil as a result of saturated soil conditions or where soil concretions have formed. Typical colors are gray mottlings, solid gray, or black. The depth in the soil at which these conditions first occur is termed the seasonal high water table.

"State Water Control Law" means Chapter 3.1 (§ 62.1-44.2 et.seq.) of Title 62.1 of the Code of Virginia.

"Treatment works" means (i) a waste holding pond or tank used to store manure prior to land application or (ii) a lagoon or treatment facility used to digest or reduce the solids or nutrients.

"Vegetated buffer" means a permanent strip of dense perennial vegetation established parallel to the contours of and perpendicular to the dominant slope of the field for the purposes of slowing water runoff, enhancing water infiltration, and minimizing the risk of any potential nutrients or pollutants from leaving the field and reaching surface waters.

"Waste nutrient analysis rate" means a land application rate for animal waste approved by the board as specified in this regulation.

"Waste storage facility" means (i) a waste holding pond or tank used to store manure prior to land application, (ii) a lagoon or treatment facility used to digest or reduce the solids or nutrients, or (iii) a structure used to store manure or waste.

"Vegetated buffer" means a permanent strip of dense perennial vegetation established parallel to the contours of and perpendicular to the dominant slope of the field for the purposes of slowing water runoff, enhancing water infiltration, and minimizing the risk of any potential nutrients or pollutants from leaving the field and reaching surface waters.

"300 animal units" means 300,000 pounds of live animal weight, or the following numbers and types of animals:

a. 300 slaughter and feeder cattle;

b. 200 mature dairy cattle (whether milked or dry cows);

c. 750 swine each weighing over 25 kilograms (approximately 55 pounds);

d. 150 horses;

e. 3,000 sheep or lambs;

f. 16,500 turkeys;

g. 30,000 laying hens or broilers.

9VAC25-192-15 Applicability of incorporated references based on the dates that they became effective

Except as noted, when a regulation of the U.S. Environmental Protection Agency (EPA) set forth in Title 40 of the Code of Federal Regulations is referenced or adopted in this chapter and incorporated by reference, that regulation shall be as it exists and has been published as of July 1, 2023.

9VAC25-192-20 Purpose; effective date of the general permit

A. This general permit regulation chapter governs the pollutant management activities at animal feeding operations having 300 or more animal units utilizing a liquid manure collection and storage system not covered by a Virginia Pollutant Discharge Elimination System (VPDES) permit and animal waste utilized or stored by animal waste end-users. These The owners of animal feeding operations may operate run and maintain treatment works for waste storage, treatment, or recycling and may perform land application of manure, wastewater, compost, or sludges.

B. This general permit will become effective on November 16, 2014 2024. This general permit will expire 10 years from the effective date on November 15, 2034.

9VAC25-192-25 Duty to comply

A. Any No person who manages or proposes to manage pollutants regulated by 9VAC25-192 comply with the applicable requirements of this chapter shall operate an animal feeding operation with 300 or more animal units utilizing a liquid manure collection and storage system after July 1, 2000, without having submitted a registration statement as provided in 9VAC25-192-60 or being covered by a Virginia Pollutant Discharge Elimination System (VPDES) permit or an individual Virginia Pollution Abatement (VPA) permit.

B. In order to manage pollutants from an animal feeding operation, the owner shall be required to obtain coverage under the Virginia Pollution Abatement (VPA) general permit or an individual VPA permit provided that the owner has not been required to obtain a Virginia Pollutant Discharge Elimination System (VPDES) permit. The owner shall comply with the requirements of this chapter and the permit.

C. An animal waste end-user shall comply with the technical requirements outlined in 9VAC25-192-80 and 9VAC25-192-90.

9VAC25-192-50 Authorization to manage pollutants

A. Owner of an animal feeding operation. Any An owner governed by of an animal feeding operation that is subject to this general permit is hereby authorized to manage pollutants at the animal feeding operations provided that the owner files the a registration statement of in accordance with 9VAC25-192-60, complies with the requirements of 9VAC25-192-70, and provided that:

1. The owner has not been required to obtain a Virginia Pollutant Discharge Elimination System (VPDES) permit or an individual Virginia Pollution Abatement (VPA) permit according to subdivision 2 of 9VAC25-32-260.

2. The operation of the animal feeding operation shall not contravene the Water Quality Standards, as amended, and adopted by the board, (9VAC25-260) or any provision of the State Water Control Law. There shall be no point source discharge of wastewater to surface waters of the state except in the case of a storm event greater than the 25-year, 24-hour storm. Agricultural stormwater discharges are permitted. Domestic sewage shall not be managed under this general permit. Industrial waste wastes shall not be managed under this general permit, except for wastes that have been approved by the department and are managed in accordance with 9VAC25-192-70.

3. The owner of any proposed pollutant management activities or those which have not previously been issued a valid Virginia Pollution Abatement (VPA) general permit or an individual VPA permit or Virginia Pollutant Discharge Elimination System (VPDES) permit must attach a Local Government Ordinance Form to the registration statement, the Local Government Ordinance Form (a notification from the governing body of the county, city or town where the operation is located that the operation is consistent with all ordinances adopted pursuant to Chapter 22 (§ 15.2-2200 et seq.) of Title 15.2 of the Code of Virginia).

4. The owner shall obtain Department of Conservation and Recreation approval of a nutrient management plan for the animal feeding operation prior to the submittal of the registration statement. The owner shall attach to the registration statement a copy of the approved nutrient management plan and a copy of the letter from the Department of Conservation and Recreation certifying approval of the nutrient management plan that was developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia. The owner shall implement the approved nutrient management plan.

5. a. The owner shall give notice of the registration statement to all owners or residents of property that adjoins the property on which the animal feeding operation will be located.

a. Such notice shall include (i) the types and maximum number of animals which that will be maintained at the animal feeding operation and (ii) the address and phone number of the appropriate department regional office to which comments relevant to the registration statement may be submitted. This notice requirement is waived whenever registration is for the purpose of renewing coverage under this general permit and no expansion is proposed and the department has not issued any special order or consent order relating to violations under this existing general permit.

b. Any person may submit written comments on the proposed operation to the department within 30 days of the date of the filing of the registration statement. If, on the basis of based on such written comments or his the director's review, the director determines that the proposed operation will not be capable of complying with the provisions of the this general permit, then the director shall require the owner to obtain an individual VPA permit for the operation. Any such determination by the director shall be made in writing and mailed to the owner not more than 45 days after the filing of the registration statement, or, if in the director's sole discretion additional time is necessary to evaluate comments received from the public, then not more than 60 days after the filing of the registration statement.

6. As required by § 62.1-44.17:1 F of the Code of Virginia, each Each owner of a facility an animal feeding operation covered by this general permit shall have completed the training program offered or approved by the department in the two years prior to submitting the registration statement for general permit coverage, or shall complete such training within one year after the registration statement has been submitted for general permit coverage. All permitted owners shall complete the training program at least once every three years.

B. Animal waste end-user. An animal waste end-user shall comply with the requirements outlined in 9VAC25-192-80 and 9VAC25-192-90.

1. When an animal waste end-user does not comply with the requirements of 9VAC25-192-80 and 9VAC25-192-90, the department may choose to do any or all of the following:

a. Initiate enforcement action based upon the violation of the regulation;

b. Require the animal waste end-user to register for coverage under the this general permit or apply for an individual VPA permit; and

c. Require the animal waste end-user to apply for the VPA individual permit; or

d. Take other actions set forth in the VPA Permit Regulation (9VAC25-32).

2. An When an animal waste end-user governed by is required to register for coverage under this general permit, the end-user is hereby authorized to manage pollutants relating to the utilization and storage of store animal waste provided that the animal waste end-user files the registration statement of 9VAC25-192-60, complies with the requirements of 9VAC25-192-70, and:

a. The animal waste end-user has not been required to obtain a an individual VPA individual permit according to subdivision 2 of 9VAC25-32-260;

b. The activities of the animal waste end-user shall not contravene the Water Quality Standards, as amended, and adopted by the board, (9VAC25-20-260) or any provision of the State Water Control Law (§ 62.1-44 et seq. of the Code of Virginia). There shall be no point source discharge of wastewater to surface waters of the state except in the case of a storm event greater than the 25-year, 24-hour storm. Agricultural stormwater discharges are permitted. Domestic sewage shall not be managed under this general permit. Industrial waste wastes shall not be managed under this general permit, except for wastes that have been approved by the department and are managed in accordance with 9VAC25-192-70;

c. The animal waste end-user shall obtain Department of Conservation and Recreation approval of a nutrient management plan for land application sites where animal waste will be utilized or stored and managed prior to the submittal of the registration statement. The animal waste end-user shall attach to the registration statement a copy of the approved nutrient management plan and a copy of the letter from the Department of Conservation and Recreation certifying approval of the nutrient management plan that was developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia. The animal waste end-user shall implement the approved nutrient management plan; and

d. As required by § 62.1-44.17:1 F of the Code of Virginia, each Each permitted animal waste end-user shall complete a training program offered or approved by the department within one year of filing the registration statement for general permit coverage. All permitted animal waste end-users shall complete a training program at least once every three years.

C. Continuation of general permit coverage.

1. In any case where the board, through no fault of the owner or permittee, does not issue the next consecutive general permit with an effective date on or before the expiration date of the expiring general permit, the following applies. Any owner that was authorized to manage pollutants under the this general permit issued in 2004 and that submits a complete registration statement on or before November 15, 2014, is authorized to continue to manage pollutants under the terms of the 2004 general permit in accordance with 9VAC25-192-60 on or before the expiration date of the expiring general permit coverage, is authorized to continue to manage pollutants under the terms of the previously issued general permit. The conditions of the expiring general permit and any requirements of coverage granted under it shall continue in force until the effective date of the next consecutive general permit and until such time as the board either:

a. Issues coverage to the owner or permittee under this the next consecutive general permit; or

b. Notifies the owner or permittee that coverage under this the next consecutive general permit is denied.

2. When the permittee that was covered under the expiring or expired general permit has violated or is violating the conditions of that general permit, the board department may choose to do any or all of the following:

a. Initiate enforcement action based upon the expiring or expired general permit;

b. Issue a notice of intent to deny coverage under the reissued general permit. If the general permit coverage is denied, then the owner would then will be required to cease the activities authorized by the expiring or expired general permit or be subject to enforcement action for operating without a general permit;

c. Issue an individual VPA permit with appropriate conditions; or and

d. Take other actions set forth in the VPA Permit Regulation (9VAC25-32).

D. Receipt of this general permit does not relieve any permittee of the responsibility to comply with any other applicable federal, state, or local statute, ordinance, or regulation.

9VAC25-192-60 Registration statement

A. The owner of an animal feeding operation. In order to To be covered under the this general permit, the owner shall file a complete VPA General Permit Registration Statement for the management of pollutants at animal feeding operations in accordance with this chapter. The registration statement shall be deemed complete for registration under the VPA General Permit this general permit if it contains the following information:

1. The animal feeding operation owner's name, mailing address, email address (if available), and telephone number;

2. The name, mailing address, email address (if available), and telephone number of the operator or contact person other than the owner, if applicable;

3. The farm name (if applicable) and location of the animal feeding operation;

4. The best time of day and day of the week to contact the operator or the contact person;

5. If The permit number, if the facility animal feeding operation has an existing general permit, individual VPA permit, or VPDES permit number, the permit number;

6. The type or types of animals (e.g., dairy cattle, slaughter and feeder cattle, swine, other) and the maximum number and average weight of the type or types of animals to be maintained at the animal feeding operation;

7. The types of wastes that will be managed at the facility animal feeding operation and how much of each type of waste will be managed;

8. If waste will be transferred off-site, then the type of waste and how much will be transferred;

9. The owner of any proposed pollutant management activities animal feeding operation that will manage animal waste or those which that have not previously been issued a valid general permit, an individual VPA permit, or a VPDES permit must attach the Local Government Ordinance Form to the registration statement, the Local Government Ordinance Form (the notification from the governing body of the county, city or town where the operation is located that the operation is consistent with all ordinances adopted pursuant to Chapter 22 (§ 15.2-2200 et seq.) of Title 15.2 of the Code of Virginia);

10. A copy of the nutrient management plan approved by the Department of Conservation and Recreation;

11. A copy of the Department of Conservation and Recreation nutrient management plan approval letter that also certifies that the plan was developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia; and

12. The following certification: "I certify that notice of the registration statement has been given to all owners or residents of property that adjoins the property on which the animal feeding operation will be located. This notice included the types and numbers of animals which that will be maintained at the facility animal feeding operation and the address and phone number of the appropriate Department of Environmental Quality regional office to which comments relevant to the this general permit may be submitted. (The preceding certification is waived if the registration is for renewing coverage under the this general permit, and no expansion of the operation is proposed, and the department has not issued any special order or consent order relating to violations under the existing general permit.) I certify under penalty of law that all the requirements of the board for the this general permit are being met and that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure ensure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations."

B. The animal waste end-user. In order to To be covered under the this general permit, the animal waste end-user shall file a complete VPA General Permit Registration Statement in accordance with this chapter. The registration statement shall be deemed complete for registration under the VPA General Permit this general permit if it contains the following information:

1. The animal waste end-user's name, mailing address, email address (if available), and telephone number;

2. The name (if applicable) and location of the facility where the animal waste will be utilized, stored, or managed;

3. The best time of day and day of the week to contact the animal waste end-user;

4. If The permit number if the facility animal waste end-user has an existing general permit, an individual VPA permit, or a VPDES permit number, the permit number;

5. If confined animals are located at the facility also confined, then indicate the type or types of animals (e.g., dairy cattle, slaughter and feeder cattle, swine, other) and the maximum number and average weight of the type or types of animals;

6. The types of wastes that will be managed at the facility by the animal waste end-user and how much of each type of waste will be managed;

7. If waste will be transferred off-site, then the type of waste and how much will be transferred;

8. A copy of the nutrient management plan approved by the Department of Conservation and Recreation;

9. A copy of the Department of Conservation and Recreation nutrient management plan approval letter that also certifies that the plan was developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia; and

10. The following certification: "I certify under penalty of law that all the requirements of the board for the this general permit are being met and that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure ensure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is to the best of my knowledge and belief true, accurate, and complete. I am aware that there are significant penalties for submitting false information including the possibility of fine and imprisonment for knowing violations."

C. The registration statement shall be signed in accordance with Part II F of subdivision 1 of 9VAC25-32-70.

9VAC25-192-70 Contents of the general permit

Any owner or animal waste end-user whose registration statement is accepted by the board department will receive the following general permit and shall comply with the requirements therein of the general permit and be subject to the VPA permit regulation Permit Regulation, 9VAC25-32.

General Permit No.: VPG1
Effective Date: November 16, 2014 2024
Expiration Date: November 15, 2024 2034

GENERAL PERMIT FOR POLLUTANT MANAGEMENT ACTIVITIES FOR ANIMAL FEEDING OPERATIONS AND ANIMAL WASTE MANAGEMENT

AUTHORIZATION TO MANAGE POLLUTANTS UNDER THE VIRGINIA POLLUTION ABATEMENT PROGRAM AND THE VIRGINIA STATE WATER CONTROL LAW

In compliance with the provisions of the State Water Control Law and State Water Control Board regulations adopted pursuant thereto, owners of animal feeding operations having 300 or more animal units utilizing a liquid manure collection and storage system, and animal waste end-users are authorized to manage pollutants within the boundaries of the Commonwealth of Virginia, except where board regulations prohibit such activities.

The authorized pollutant management activities shall be in accordance with the registration statement, supporting documents submitted to the Department of Environmental Quality, this cover page, Part I-Pollutant Management and Monitoring Requirements for Animal Feeding Operations, Part II-Conditions Applicable to all VPA Permits this General Permit, and Part III-Pollutant Management and Monitoring Requirements for Animal Waste End-Users, as set forth herein in this section.

Part I

Pollutant Management and Monitoring Requirements for Animal Feeding Operations

A. Pollutant management and monitoring requirements.

1. During the period beginning with the this general permit's effective date and lasting until the this general permit's expiration date, the permittee is authorized to manage pollutants at the location or locations identified in the registration statement and the facility's approved nutrient management plan written for the animal feeding operation.

2. At earthen liquid waste storage facilities constructed after December 1, 1998, to an elevation below the seasonal high water table or within one foot thereof, groundwater monitoring wells shall be installed. A minimum of one up gradient and one down gradient well shall be installed at each earthen waste storage facility that requires groundwater monitoring. Existing wells may be utilized to meet this requirement if properly located and constructed.

3. All facilities animal feeding operations previously covered under a general permit, an individual VPA permit, or a VPDES permit that required groundwater monitoring shall continue monitoring consistent with the requirements listed below in this part regardless of where they the animal feeding operations are located relative to the seasonal high water table.

4. At facilities animal feeding operations where groundwater monitoring is required, the following conditions apply:

a. One data set shall be collected from each well prior to any waste being placed in the storage facility.

b. The static water level shall be measured prior to bailing well water for sampling.

c. At least three well volumes of groundwater shall be withdrawn immediately prior to sampling each monitoring well.

5. In accordance with subdivisions 2 and 3 of this subsection, the groundwater shall be monitored by the permittee at the monitoring wells as specified below in Table 1 of Part I. Additional groundwater monitoring may be required in the facility's approved nutrient management plan written for the animal feeding operation.

6. If groundwater monitoring results for any monitored parameter demonstrate potential noncompliance with this general permit related to the waste storage facility, then the permittee shall submit an approvable groundwater monitoring action plan that outlines appropriate measures to be taken to address the noncompliance. The groundwater monitoring action plan shall be submitted to the department within 30 days of obtaining the monitoring results.

7. The analysis of the groundwater samples for ammonia nitrogen and nitrate nitrogen shall be performed by a laboratory accredited under the Virginia Environmental Laboratory Accreditation Program (VELAP) in accordance with 1VAC30-46-20. Field sampling, testing, and measurement of the static water level, pH, and conductivity where the sample is taken are not subject to the VELAP requirement.

TABLE 1

GROUNDWATER MONITORING

PARAMETERS

LIMITATIONS

UNITS

MONITORING REQUIREMENTS

Frequency

Sample Type

Static Water Level

NL

Ft

1/3 years

Measured

Ammonia Nitrogen

NL

mg/L

1/3 years

Grab

Nitrate Nitrogen

NL

mg/L

1/3 years

Grab

pH

NL

SU

1/3 years

Grab

Conductivity

NL

umhos/cm µmhos/cm

1/3 years

Grab

NL = No limit, this is a monitoring requirement only.

6. 8. Soil at the land application sites shall be monitored as specified below in Table 2 of Part I. Additional soils monitoring may be required in the facility's approved nutrient management plan written for the animal feeding operation.

TABLE 2

SOILS MONITORING

PARAMETERS

LIMITATIONS

UNITS

MONITORING REQUIREMENTS

Frequency

Sample Type

pH

NL

SU

1/3 years

Composite

Phosphorus

NL

ppm or lbs/ac

1/3 years

Composite

Potash

NL

ppm or lbs/ac

1/3 years

Composite

Calcium

NL

ppm or lbs/ac

1/3 years

Composite

Magnesium

NL

ppm or lbs/ac

1/3 years

Composite

NL = No limit, this is a monitoring requirement only.

SU = Standard Units

7. 9. Soil monitoring shall be conducted at a depth of between 0-6 inches, unless otherwise specified in the facility's approved nutrient management plan written for the animal feeding operation.

8. 10. Waste shall be monitored as specified below in Table 3 of Part I. Additional waste monitoring may be required in the facility's approved nutrient management plan written for the animal feeding operation.

TABLE 3

WASTE MONITORING

PARAMETERS

LIMITATIONS

UNITS

MONITORING REQUIREMENTS

Frequency

Sample Type

Total Kjeldahl Nitrogen

NL

*

1/year

Composite

Ammonia Nitrogen

NL

*

1/year

Composite

Total Phosphorus

NL

*

1/year

Composite

Total Potassium

NL

*

1/year

Composite

Calcium

NL

*

1/year

Composite

Magnesium

NL

*

1/year

Composite

Moisture Content

NL

%

1/year

Composite

NL = No limit, this is a monitoring requirement only.

*Parameters for waste may be reported as a percent, as lbs/ton or lbs/1000 gallons, or as ppm where appropriate.

9. 11. Analysis of soil and waste shall be according to methods specified in the facility's approved nutrient management plan written for the animal feeding operation.

10. 12. All monitoring data collected as required by this section and any additional monitoring shall be maintained on site for a period of five years and shall be made available to department personnel upon request.

B. Other Site design, storage, and operations requirements or special conditions.

1. Any liquid manure collection and storage facility shall be designed and operated to (i) prevent point source discharges of pollutants to state waters except in the case of a storm event greater than the 25-year, 24-hour storm and (ii) provide adequate waste storage capacity to accommodate periods when the ground is frozen or saturated, periods when land application of nutrients should not occur due to limited or nonexistent crop nutrient uptake, and periods when physical limitations prohibit the land application of waste.

2. Waste storage facilities constructed after December 1, 1998, shall not be located on a 100-year floodplain. For the purposes of determining the 100-year floodplain, a Federal Emergency Management Agency (FEMA) Flood Insurance Rate Map (FIRM), a FEMA Letter of Map Amendment (LOMA), or a FEMA Letter of Map Revision (LOMR) shall be used.

3. Earthen waste storage facilities constructed after December 1, 1998, shall include a properly designed and installed liner. Such liner shall be either a synthetic liner of at least 20 mils thickness or a compacted soil liner of at least one foot thickness with a maximum permeability rating of 0.0014 inches per hour. A Virginia licensed professional engineer or an employee of the Natural Resources Conservation Service of the United States U.S. Department of Agriculture with appropriate engineering approval authority shall certify that the siting, design, and construction of the waste storage facility comply with the requirements of this general permit. This certification shall be maintained on site.

4. At earthen waste storage facilities constructed below the seasonal high water table, the top surface of the waste must be maintained at a level of at least two feet above the water table.

5. All liquid waste storage or treatment facilities shall maintain at least one foot of freeboard at all times, up to and including a 25-year, 24-hour storm.

6. For new waste storage or treatment facilities constructed after November 16, 2014, the facilities shall be constructed, operated, and maintained in accordance with the applicable practice standard adopted by the Natural Resources Conservation Service of the U.S. Department of Agriculture and approved by the department. A Virginia licensed professional engineer or an employee of the Natural Resources Conservation Service of the U.S. Department of Agriculture with appropriate engineering approval authority shall certify that the siting, design, and construction of the waste storage facility comply with the requirements of this general permit. This certification shall be maintained on site.

7. The permittee shall notify the department's regional office at least 14 days prior to (i) animals being initially placed in the confined facility animal feeding operation or (ii) the utilization of any new waste storage or treatment facilities.

8. Semi-solid and solid waste shall be stored in a manner that prevents contact with surface water and groundwater. Waste that is stockpiled outside for more than 14 days shall be kept in a waste storage facility or at a site that provides adequate storage. Adequate storage shall, at a minimum, include the following:

a. Waste shall be covered to protect it from precipitation and wind;

b. Stormwater shall not run onto or under the stored waste;

c. A minimum of two feet separation distance to the seasonal high water table or an impermeable barrier shall be used under the stored waste. All waste storage facilities that use an impermeable barrier shall maintain a minimum of one foot separation between the seasonal high water table and the impermeable barrier. "Seasonal high water table" means that portion of the soil profile where a color change has occurred in the soil as a result of saturated soil conditions or where soil concretions have formed. Typical colors are gray mottlings, solid gray, or black. The depth in the soil at which these conditions first occur is termed the seasonal high water table. Impermeable barriers shall be constructed of at least 12 inches of compacted clay, at least four inches of reinforced concrete, or another material of similar structural integrity that has a minimum permeability rating of 0.0014 inches per hour (1X10-6 centimeters per second); and

d. For waste that is not stored in a waste storage facility or under roof, the storage site must be at least 100 feet from any surface water, intermittent drainage, wells, sinkholes, rock outcrops, and springs. For semi-solid and solid waste that is stored on an impermeable barrier and where any stormwater runoff is collected in the waste storage facility, the semi-solid and solid waste can be stored adjacent to the waste storage facility regardless of the location of the waste storage facility so long as any surface water, intermittent drainage, wells, sinkholes, rock outcrops, and springs are protected from runoff from the stored semi-solid and solid waste.

Semi-solid and solid waste that is stored on an impermeable barrier and where any stormwater runoff is collected in a waste storage facility is considered adequate storage and is therefore not required to be covered.

9. All equipment needed for the proper operation of the permitted facilities animal feeding operations shall be maintained in good working order. The manufacturer's operating and maintenance manuals shall be retained for references to allow for timely maintenance and prompt repair of equipment when appropriate. The permittee shall periodically inspect for leaks on equipment used for land application of waste.

10. When wastes are treated by a digester or other manure treatment technologies, the waste treatment process shall be approved by the department and shall be managed by a facility the owner of an animal feeding operation covered under this general permit and in accordance with the following conditions:

a. All treated wastes generated by a digester or other manure treatment technologies must be managed through an approved nutrient management plan or transferred to another entity in accordance with animal waste transfer requirements in Part 1 B 15 C 6 and 16 7.

b. When a facility an animal feeding operation covered under this general permit generates a treated waste from animal waste and other feedstock, the permittee shall maintain records related to the production of the treated waste.

(1) If off-site wastes are added to generate the treated waste, then the permittee shall record the following items:

(a) The amount of waste brought to the facility animal feeding operation; and

(b) From whom and where the waste originated.

(2) For all treated wastes generated by the facility animal feeding operation, the permittee shall record the following items:

(a) The amount of treated waste generated;

(b) The nutrient analysis of the treated waste; and

(c) The final use of the treated waste.

(3) Permittees shall maintain the records required by Part I B 10 b (1) and (2) on site for a period of three years. All records shall be made available to department personnel upon request.

11. When the waste storage facility is no longer needed, the permittee shall close it in a manner that (i) minimizes the need for further maintenance and (ii) controls, minimizes, or eliminates, to the extent necessary to protect human health and the environment, the postclosure escape of uncontrolled leachate, surface runoff, or waste decomposition products to the groundwater, surface water, or the atmosphere. Prior to closure, the permittee shall notify the department of any plans to close a liquid waste storage facility. At closure, the permittee shall remove all waste residue from the animal waste storage facility. Removed waste materials shall be utilized according to the approved NMP.

C. Animal waste use and transfer requirements.

1. Animal waste generated by this facility an animal feeding operation that is subject to this general permit shall not be applied to fields owned by or under the operational control of either the permittee or a legal entity in which the permittee has an ownership interest unless the fields are included in the facility's approved nutrient management plan written for the animal feeding operation.

12. 2. The permittee shall implement a nutrient management plan (NMP) developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia and approved by the Department of Conservation and Recreation and maintain the plan NMP on site. All revised and Department of Conservation and Recreation approved NMPs shall be submitted to the department prior to the expiration of the previous NMP. The NMP shall address the form, source, amount, timing, and method of application of nutrients on each field to achieve realistic production goals, while minimizing nitrogen and phosphorus loss to ground waters and surface waters. The terms of the NMP shall be enforceable through this general permit. The NMP shall contain at a minimum the following information:

a. Site map indicating the location of the waste storage facilities and the fields where waste will be applied;

b. Site evaluation and assessment of soil types and potential productivities;

c. Nutrient management sampling, including soil and waste monitoring;

d. Storage and land area requirements;

e. Calculation of waste application rates; and

f. Waste application schedules.

13. 3. Waste shall not be land applied within buffer zones. Buffer zones at waste application sites shall, at a minimum, be maintained as follows:

a. Distance from occupied dwellings not on the permittee's property: 200 feet (unless the occupant of the dwelling signs a waiver of the buffer zone);

b. Distance from water supply wells or springs: 100 feet;

c. Distance from surface water courses: 100 feet (without a permanent vegetated buffer) or 35 feet (if a permanent vegetated buffer exists). Other site-specific conservation practices may be approved by the department that will provide pollutant reductions equivalent or better than the reductions that would be achieved by the 100-foot buffer or 35-foot wide vegetated buffer;

d. Distance from rock outcropping (except limestone): 25 feet;

e. Distance from limestone outcroppings: 50 feet; and

f. Waste shall not be applied in such a matter that it would discharge to sinkholes that may exist in the area.

14. 4. The following land application records shall be maintained:

a. The identification of the land application field sites where the waste is utilized or stored;

b. The application rate;

c. The application dates; and

d. What crops have been planted.

These records shall be maintained on site for a period of five years after the date the application is made and shall be made available to department personnel upon request.

5. In cases where a waste storage facility is threatened by emergencies such as fire or flood or where these conditions are imminent, animal waste can be land applied outside of the spreading schedule outlined in the NMP written for an animal feeding operation. If this occurs, then the owner of the animal feeding operation shall document the land application information in accordance with Part I C 4 and notify the department in accordance with Part II F 3.

15. 6. Animal waste generated by this facility an animal feeding operation that is subject to this general permit may be transferred from the permittee to another person if one or more of the following conditions are met:

a. Animal waste generated by this facility an animal feeding operation that is subject to this general permit may be transferred off-site for land application or another acceptable use approved by the department, if:

(1) The sites where the animal waste will be utilized are included in this permitted facility's the animal feeding operation's approved nutrient management plan; or

(2) The sites where the animal waste will be utilized are included in another permitted facility's entity's approved nutrient management plan.

b. Animal waste generated by this facility an animal feeding operation that is subject to this general permit may be transferred off-site without identifying in the permittee's approved nutrient management plan the fields where such waste will be utilized, if one of the following conditions are met:

(1) The animal waste is registered with the Virginia Department of Agriculture and Consumer Services in accordance with regulations adopted pursuant to subdivision A 2 of § 3.2-3607 A 2 of the Code of Virginia; or

(2) When the permittee transfers to another person more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) in any 365-day period, the permittee shall maintain records in accordance with Part I B 16 C 7.

16. 7. Animal waste may be transferred from a permittee to another person without identifying the fields where such waste will be utilized in the permittee's approved nutrient management plan if the following conditions are met:

a. When a permittee transfers to another person more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) in any 365-day period, the permittee shall provide that person with:

(1) Permittee's name, address, and permit number;

(2) A copy of the most recent nutrient analysis of the animal waste; and

(3) An animal waste fact sheet.

b. When a permittee transfers to another person more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) in any 365-day period, the permittee shall keep a record of the following:

(1) The recipient recipient's name and address;

(2) The amount of animal waste received by the person;

(3) The date of the transaction;

(4) The nutrient analysis of the animal waste;

(5) The locality in which the recipient intends to utilize the animal waste (i.e., nearest town or city and zip code);

(6) The name of the stream or waterbody, if known, to the recipient that is nearest to the animal waste utilization or storage site; and

(7) The signed waste transfer records form acknowledging the receipt of the following:

(a) The animal waste;

(b) The nutrient analysis of the animal waste; and

(c) An animal waste fact sheet.

c. Permittees shall maintain the records required by Part I B 16 C 7 a and b for at least three years after the date of the transaction and shall make them available to department personnel upon request.

17. When the waste storage or treatment facility is no longer needed, the permittee shall close it in a manner that (i) minimizes the need for further maintenance and (ii) controls, minimizes, or eliminates, to the extent necessary to protect human health and the environment, the postclosure escape of uncontrolled leachate, surface runoff, or waste decomposition products to the groundwater, surface water, or the atmosphere. At closure, the permittee shall remove all waste residue from the animal waste storage or treatment facility. Removed waste materials shall be utilized according to the approved NMP.

18. As required by § 62.1-44.17:1 F of the Code of Virginia, each D. Each permittee covered under this general permit shall have completed the training program offered or approved by the department in the two years prior to submitting the registration statement for this general permit coverage, or shall complete such training within one year after the registration statement has been submitted for this general permit coverage. All permittees shall complete the training program at least once every three years.

Part II
Conditions Applicable to all VPA Permits this General Permit

A. Sampling and analysis methods Monitoring.

1. Samples and measurements taken as required by this general permit shall be representative of the volume and nature of the monitored activity.

2. Unless otherwise specified in this permit all sample preservation methods, maximum holding times and analysis methods for pollutants Groundwater monitoring shall comply with requirements set forth in Guidelines Establishing Test Procedures for the Analysis of Pollutants (40 CFR Part 136) be conducted according to procedures listed under 40 CFR Part 136 unless otherwise specified in this general permit.

3. The sampling and analysis program to demonstrate compliance with the permit shall at a minimum, conform to Part I of this permit.

4. The permittee shall periodically calibrate and perform maintenance procedures on all monitoring and analytical instrumentation at intervals that will ensure accuracy of measurements.

4. If the permittee monitors any pollutant at the locations designated in this general permit more frequently than required by this general permit, using approved analytical methods as specified in this part, the results of such monitoring shall be included in the calculation and reporting of the values required in the project report. Such increased frequency shall also be reported.

B. Recording of results Records. For each measurement or sample taken pursuant to the requirements of this permit, the permittee shall record the following

1. Records of monitoring information shall include:

1. a. The date, exact place, and time of sampling or measurements;

2. b. The persons name of the individuals who performed the sampling or measurements;

3. c. The dates analyses were performed;

4. d. The persons name of the individuals who performed each analysis;

5. e. The analytical techniques or methods used with supporting information such as observations, readings, calculations, and bench data; and

6. f. The results of such analyses and measurements.

2. The permittee shall retain records of all monitoring information, including all calibration and maintenance records and all original strip chart recordings for continuous monitoring instrumentation, copies of all reports required by this general permit, and records of all data used to complete the application for this general permit for a period of at least three years from the date of the sample, measurement, report, or application. This period of retention may be extended by request of the department at any time.

C. Records retention Reporting monitoring results. All records and information resulting from the monitoring activities If reporting is required by Part I or Part III of this general permit, including all records of analyses performed and calibration and maintenance of instrumentation and recording from continuous monitoring instrumentation the permittee shall be retained on site for five years from the date of the sample, measurement or report. This period of retention shall be extended automatically during the course of any unresolved litigation regarding the regulated activity or regarding control standards applicable to the permittee, or as requested by the director follow the requirements of this subsection.

1. The permittee shall submit the results of the monitoring required by this general permit not later than the 10th day of the month after the monitoring takes place, unless another reporting schedule is specified elsewhere in this general permit. Monitoring results shall be submitted to the department's regional office.

2. Monitoring results shall be reported on forms provided or specified by the department.

3. If the permittee monitors the pollutant management activity, at a sampling location specified in this general permit, for any pollutant more frequently than required by this general permit using approved analytical methods, the permittee shall report the results of this monitoring on the monitoring report.

4. If the permittee monitors the pollutant management activity, at a sampling location specified in this general permit, for any pollutant that is not required to be monitored by the general permit, and uses approved analytical methods, the permittee shall report the results with the monitoring report.

5. Calculations for all limitations that require averaging of measurements shall utilize an arithmetic mean unless otherwise specified in this general permit.

D. Additional monitoring by permittee Duty to provide information. If the permittee monitors any pollutant at the locations designated herein more frequently than required by this permit, using approved analytical methods as specified above, the results of such monitoring shall be included in the calculation and reporting of the values required in the project report. Such increased frequency shall also be reported. The permittee shall furnish to the department, within a reasonable time, any information that the director may request to determine whether cause exists for modifying, revoking and reissuing, or terminating this general permit or to determine compliance with this general permit. The permittee shall also furnish to the department, upon request, copies of records required to be kept by the permittee. Plans, specifications, maps, conceptual reports, and other relevant information shall be submitted as requested by the director prior to commencing construction.

E. Reporting requirements Unauthorized discharges. Except in compliance with this general permit or another issued by the department, it shall be unlawful for any person to:

1. If, for any reason, the permittee does not comply with one or more limitations, standards, monitoring or management requirements specified in this permit, the permittee shall submit to the department at least the following information:

a. A description and cause of noncompliance;

b. The period of noncompliance, including exact dates and times or the anticipated time when the noncompliance will cease; and

c. Actions taken or to be taken to reduce, eliminate, and prevent recurrence of the noncompliance. Whenever such noncompliance may adversely affect state waters or may endanger public health, the permittee shall submit the above required information by oral report within 24 hours from the time the permittee becomes aware of the circumstances and by written report within five days. The director may waive the written report requirement on a case-by-case basis if the oral report has been received within 24 hours and no adverse impact on state waters has been reported.

2. The permittee shall report any unpermitted, unusual or extraordinary discharge which enters or could be expected to enter state waters. The permittee shall provide information, specified in Part II E 1 a through c, regarding each such discharge immediately, that is, as quickly as possible upon discovery, however, in no case later than 24 hours. A written submission covering these points shall be provided within five days of the time the permittee becomes aware of the circumstances covered by this paragraph.

NOTE: The immediate (within 24 hours) reports required in Parts II E 1 and 2 may be made to the department's regional office. Reports may be made by telephone. For reports outside normal working hours, a message shall fulfill the immediate reporting requirement. For emergencies, the Virginia Department of Emergency Management maintains a 24-hour telephone service at 1-800-468-8892.

1. Discharge into state waters sewage, industrial wastes, other wastes, or any noxious or deleterious substances; or

2. Otherwise alter the physical, chemical, or biological properties of such state waters and make them detrimental to the public health or to animal or aquatic life or to the use of such waters for domestic or industrial consumption or for recreation or for other uses.

F. Signatory requirements Notice of planned changes, and reports of unauthorized discharges, unusual or extraordinary discharges, noncompliance, and compliance schedules. Any registration statement or certification required by this permit shall be signed as follows:

1. For a corporation, by a responsible corporate official Notice of planned changes. For purposes of this section, a responsible corporate official means (i) a president, secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or any other person who performs similar policy or decision-making functions for the corporation, or (ii) the manager of one or more manufacturing, production, or operating facilities employing more than 250 persons or having gross annual sales or expenditures exceeding $25,000,000 (in second quarter 1980 dollars), if authority to sign documents has been assigned or delegated to the manager in accordance with corporate procedures.

a. The permittee shall give notice to the department as soon as possible of any planned physical alterations or additions to the design or operation of the pollutant management activity.

b. The permittee shall give at least 10 days advance notice to the department of any planned changes in the permitted facility or activity that may result in noncompliance with the general permit requirements.

2. For a municipality, state, federal or other public agency by either a principal executive officer or ranking elected official Reports of unauthorized discharges. (A principal executive officer of a federal, municipal, or state agency includes the chief executive officer of the agency or head executive officer having responsibility for the overall operation of a principal geographic unit of the agency.) Any permittee who discharges or causes or allows (i) a discharge of sewage, industrial wastes, other wastes, or any noxious or deleterious substance into or upon state waters in violation of Part II E, or (ii) a discharge that may reasonably be expected to enter state waters in violation of Part II E shall notify the department of the discharge immediately upon discovery of the discharge, but in no case later than 24 hours after said discovery. A written report of the unauthorized discharge shall be submitted to the department within five days of discovery of the discharge. The written report shall contain:

a. A description of the nature and location of the discharge;

b. The cause of the discharge;

c. The date on which the discharge occurred;

d. The length of time that the discharge continued;

e. The volume of the discharge;

f. If the discharge is continuing, how long it is expected to continue;

g. If the discharge is continuing, what the expected total volume of the discharge will be; and

h. Any steps planned or taken to reduce, eliminate, and prevent a recurrence of the present discharge or any future discharges not authorized by this general permit.

Discharges reportable to the department under the immediate reporting requirements of other regulations are exempted from this requirement.

3. For a partnership or sole proprietorship, by a general partner or proprietor respectively Reports of unusual or extraordinary discharges. If any unusual or extraordinary discharge, including a bypass or upset, should occur from a treatment works and the discharge enters or could be expected to enter state waters, the permittee shall promptly notify, in no case later than 24 hours, the department by telephone after the discovery of the discharge. This notification shall provide all available details of the incident, including any adverse effects on aquatic life and the known number of fish killed. The permittee shall reduce the report to writing and shall submit it to the department within five days of discovery of the discharge in accordance with Part II F 4 b. Unusual and extraordinary discharges include any discharge resulting from:

a. Unusual spillage of materials resulting directly or indirectly from processing operations;

b. Breakdown of processing or accessory equipment;

c. Failure or taking out of service some or all of the treatment works; and

d. Flooding or other acts of nature.

4. Reports of noncompliance. The permittee shall report any noncompliance that may adversely affect state waters or may endanger public health.

a. An oral report shall be provided within 24 hours from the time the permittee becomes aware of the circumstances. The following shall be included as information that shall be reported within 24 hours under this subdivision 4 a:

(1) Any unanticipated bypass; and

(2) Any upset that causes a discharge to surface waters.

b. A written report shall be submitted within five days and shall contain:

(1) A description of the noncompliance and its cause;

(2) The period of noncompliance, including exact dates and times, and if the noncompliance has not been corrected, the anticipated time it is expected to continue; and

(3) Steps taken or planned to reduce, eliminate, and prevent reoccurrence of the noncompliance.

The department may waive the written report on a case-by-case basis for reports of noncompliance under Part II F 4 if the oral report has been received within 24 hours and no adverse impact on state waters has been reported.

c. The permittee shall report all instances of noncompliance not reported under Part II F 4 a or b in writing at the time the next monitoring reports are submitted. The reports shall contain the information listed in Part II F 4 b.

NOTE: The immediate (within 24 hours) reports required in Part II F may be made to the department's regional office. For reports outside normal working hours, leave a message and this shall fulfill the immediate reporting requirement. For emergencies, the Virginia Department of Emergency Management maintains a 24-hour telephone service at 1-800-468-8892.

5. Reports of compliance or noncompliance with, or any progress reports on, interim and final requirements contained in any compliance schedule of this general permit shall be submitted no later than 14 days following each schedule date.

G. Change in management of pollutants Proper operation and maintenance. All pollutant management activities authorized by this permit shall be made in accordance with the terms and conditions of the permit. The permittee shall submit a new registration statement 30 days prior to all expansions, production increases, or process modifications, that will result in the management of new or increased pollutants be responsible for the proper operation and maintenance of all treatment works, systems, and controls that are installed or used to achieve compliance with the conditions of this permit. Proper operation and maintenance includes effective plant performance, adequate funding, adequate staffing, and adequate laboratory and process controls, including appropriate quality assurance procedures. The management of any pollutant at a level greater than that identified and authorized by this permit, shall constitute a violation of the terms and conditions of this permit.

H. Treatment works operation and quality control Signatory requirements.

1. Design and operation of facilities or treatment works and disposal of all wastes shall be in accordance with the registration statement filed with the department. The permittee has the responsibility of designing and operating the facility in a reliable and consistent manner to meet the facility performance requirements in the permit. If facility deficiencies, design or operational, are identified in the future which could affect the facility performance or reliability, it is the responsibility of the permittee to correct such deficiencies Applications. All general permit applications shall be signed as follows:

a. For a corporation: by a responsible corporate officer. For the purpose of this section, a responsible corporate officer means (i) a president, secretary, treasurer, or vice-president of the corporation in charge of a principal business function, or any other person who performs similar policy-making or decision-making functions for the corporation or (ii) the manager of one or more manufacturing, production, or operating facilities employing more than 250 persons or having gross annual sales or expenditures exceeding $25 million (in second-quarter 1980 dollars) if authority to sign documents has been assigned or delegated to the manager in accordance with corporate procedures;

b. For a partnership or sole proprietorship: by a general partner or the proprietor, respectively; or

c. For a municipality, state, federal, or other public agency: by either a principal executive officer or ranking elected official. For purposes of this section, a principal executive officer of a public agency includes (i) the chief executive officer of the agency or (ii) a senior executive officer having responsibility for the overall operations of a principal geographic unit of the agency.

2. All waste collection, control, treatment, management of pollutant activities and disposal facilities shall be operated in a manner consistent with the following Reports and other information. All reports required by general permits and other information requested by the department shall be signed by a person described in Part II H 1 or by a duly authorized representative of that person. A person is a duly authorized representative only if:

a. At all times, all facilities and pollutant management activities shall be operated in a prudent and workmanlike manner. The authorization is made in writing by a person described in Part II H 1;

b. The permittee shall provide an adequate operating staff to carry out the operation, maintenance and testing functions required to ensure compliance with the conditions of this permit. authorization specifies either an individual or a position having responsibility for the overall operation of the regulated facility or activity, such as the position of plant manager, operator of a well or a well field, superintendent, or a position of equivalent responsibility. A duly authorized representative may thus be either a named individual or any individual occupying a named position; and

c. Maintenance of treatment facilities or pollutant management activities shall be carried out in such a manner that the monitoring and limitation requirements are not violated The written authorization is submitted to the department.

d. Collected solids shall be stored and utilized as specified in the approved nutrient management plan in such a manner as to prevent entry of those wastes (or runoff from the wastes) into state waters.

3. Changes to authorization. If an authorization under Part II H 2 is no longer accurate because a different individual or position has responsibility for the overall operation of the facility, a new authorization satisfying the requirements of Part II H 2 shall be submitted to the department prior to or together with any reports or information to be signed by an authorized representative.

4. Certification. Any person signing a document under Part II H 1 or 2 shall make the following certification: "I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to ensure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations."

I. Adverse impact Duty to comply. The permittee shall take comply with all feasible steps to minimize any adverse impact to state waters resulting from noncompliance with any limitation or limitations or conditions specified in of this general permit, and shall perform and report such accelerated or additional monitoring as is necessary to determine the nature and impact of the noncomplying limitation or limitations or conditions this chapter. Any noncompliance with this general permit or this chapter constitutes a violation of the State Water Control Law. General permit noncompliance is grounds for enforcement action; for permit termination, revocation and reissuance, or modification; or for denial of a permit renewal application. Compliance with this general permit during its term constitutes compliance for purposes of enforcement with the State Water Control Law.

J. Duty to halt, reduce activity or to mitigate reapply.

1. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this permit.

2. The permittee shall take all reasonable steps to minimize, correct or prevent any discharge in violation of this permit which has a reasonable likelihood of adversely affecting human health or the environment.

If the permittee wishes to continue an activity regulated by this general permit after the expiration date of this general permit, the permittee shall apply for and obtain a new permit. All permittees with a currently effective general permit shall submit a new application before the expiration date of the existing general permit unless permission for a later date has been granted by the board. The board shall not grant permission for applications to be submitted later than the expiration date of the existing general permit.

K. Structural stability Bypass. The structural stability of any of the units or parts of the facilities herein permitted is the sole responsibility of the permittee and the failure of such structural units or parts shall not relieve the permittee of the responsibility of complying with all terms and conditions of this permit.

1. Prohibition. "Bypass" means intentional diversion of waste streams from any portion of a treatment works. A bypass of the treatment works is prohibited except as provided in this subsection.

2. Anticipated bypass. If the permittee knows in advance of the need for a bypass, the permittee shall notify the department promptly at least 10 days prior to the bypass. After considering its adverse effects, the department may approve an anticipated bypass if:

a. The bypass will be unavoidable to prevent loss of human life, personal injury, or severe property damage. "Severe property damage" means substantial physical damage to property, damage to the treatment works that causes them to become inoperable, or substantial and permanent loss of natural resources that can reasonably be expected to occur in the absence of a bypass. "Severe property damage" does not mean economic loss caused by delays in production; and

b. There are no feasible alternatives to bypass such as the use of auxiliary treatment works, retention of untreated waste, or maintenance during normal periods of equipment downtime. However, if bypass occurs during normal periods of equipment downtime or preventive maintenance and in the exercise of reasonable engineering judgment the permittee could have installed adequate backup equipment to prevent such bypass, this exclusion shall not apply as a defense.

3. Unplanned bypass. If an unplanned bypass occurs, the permittee shall notify the department as soon as possible, but in no case later than 24 hours, and shall take steps to halt the bypass as early as possible. This notification will be a condition for defense to an enforcement action that an unplanned bypass met the conditions in Part II K 2 a and b and in light of the information reasonably available to the permittee at the time of the bypass.

L. Compliance with state law Upset. Compliance with this permit during its term constitutes compliance with the State Water Control Law. Nothing in this permit shall be construed to preclude the institution of any legal action under, or relieve the permittee from any responsibilities, liabilities, or penalties established pursuant to any other state law or regulation. A permittee may claim an upset as an affirmative defense to an action brought for noncompliance. In any enforcement proceedings a permittee shall have the burden of proof to establish the occurrence of any upset. In order to establish an affirmative defense of upset, the permittee shall present properly signed, contemporaneous operating logs or other relevant evidence that shows:

1. That an upset occurred and that the cause can be identified;

2. That the permitted facility was at the time being operated efficiently and in compliance with proper operation and maintenance procedures;

3. That the 24-hour reporting requirements to the department were met; and

4. That the permittee took all reasonable steps to minimize or correct any adverse impact on state waters resulting from noncompliance with the permit.

M. Property rights Inspection and entry. The issuance of this permit does not convey any property rights in either real or personal property, or any exclusive privileges, nor does it authorize any injury to private property or any invasion of personal rights, nor any infringement of federal, state, or local laws or regulations. Upon presentation of credentials, any duly authorized agent of the department may, at reasonable times and under reasonable circumstances:

1. Enter upon any public or private property on which the pollutant management activities that are governed by this general permit are located and have access to records required by this general permit;

2. Have access to, inspect, and copy any records that must be kept as part of the conditions in this general permit;

3. Inspect any facility's equipment (including monitoring and control equipment) practices or operations regulated or required under this general permit; and

4. Sample or monitor any substances or parameters at any locations for the purpose of assuring general permit compliance or as otherwise authorized by the State Water Control Law.

N. Severability Effect of a permit. The provisions of this permit are severable. This general permit neither conveys any property rights in either real or personal property or any exclusive privileges nor authorizes any injury to private property or invasion of personal rights or any infringement of federal, state, or local law or regulations.

O. Duty to reregister State law. If the permittee wishes to continue to operate under a general permit after the expiration date of this permit, the permittee must submit a new registration statement at least 30 days prior to the expiration date of this permit. Nothing in this general permit shall be construed to preclude the institution of any legal action under or relieve the permittee from any responsibilities, liabilities, or penalties established pursuant to any other state law or regulation or under authority preserved by § 510 of the federal Clean Water Act. Except as provided in general permit conditions on bypassing in Part II K and upset in Part II L, nothing in this general permit shall be construed to relieve the permittee from civil and criminal penalties for noncompliance.

P. Right of entry Oil and hazardous substance liability. The permittee shall allow, or secure necessary authority to allow, authorized state representatives, upon the presentation of credentials:

1. To enter upon the permittee's premises on which the establishment, treatment works, pollutant management activities, or discharge or discharges is located or in which any records are required to be kept under the terms and conditions of this permit;

2. To have access to inspect and copy at reasonable times any records required to be kept under the terms and conditions of this permit;

3. To inspect at reasonable times any monitoring equipment or monitoring method required in this permit;

4. To sample at reasonable times any waste stream, process stream, raw material or by-product; and

5. To inspect at reasonable times any collection, treatment, or pollutant management activities required under this permit. For purposes of this section, the time for inspection shall be deemed reasonable during regular business hours, and whenever the facility is discharging or involved in managing pollutants. Nothing contained here shall make an inspection time unreasonable during an emergency.

Nothing in this general permit shall be construed to preclude the institution of any legal action or relieve the permittee from any responsibilities, liabilities, or penalties to which the permittee is or may be subject under §§ 62.1-44.34:14 through 62.1-44.34:23 of the Code of Virginia.

Q. Transferability of permits Duty to mitigate. Coverage under this permit may be transferred to a new owner by a permittee if:

1. The current permittee notifies the department 30 days in advance of the proposed transfer of the title to the facility or property;

2. The notice to the department includes a written agreement between the existing and proposed new permittee containing a specific date of transfer of permit responsibility, coverage and liability between them; and

3. The department does not within the 30-day time period notify the existing permittee and the proposed permittee of the board's intent to transfer coverage under the permit. Such transferred coverage under this permit shall, as of the date of the transfer, be fully effective.

The permittee shall take all reasonable steps to minimize or prevent any pollutant management activity in violation of this general permit that has a reasonable likelihood of adversely affecting human health or the environment.

R. Permit modification Need to halt or reduce activity not a defense. The permit may be modified when a change is made in the promulgated standards or regulations on which the permit was based. It shall not be a defense for a permittee in an enforcement action that it would have been necessary to halt or reduce the permitted activity in order to maintain compliance with the conditions of this general permit.

S. Permit termination action. After public notice and opportunity for a hearing, coverage under the general permit may be terminated for cause. Permits may be modified, revoked and reissued, or terminated for cause upon the request of the permittee or interested persons or upon the department's initiative. If a permittee files a request for a general permit modification, revocation, or termination or files a notification of planned changes or anticipated noncompliance, the general permit terms and conditions shall remain effective until the request is acted upon by the department. This provision shall not be used to extend the expiration date of the effective general permit.

T. When an individual VPA permit may be required. The director may require any permittee authorized to manage pollutants covered under this general permit to apply for and obtain an individual VPA permit. Cases where an individual VPA permit may be required include, but are not limited to, the following:

1. The pollutant management activities violate the terms or conditions of this general permit;

2. When additions or alterations have been made to the affected facility that require the application of permit conditions that differ from those of the existing general permit or are absent from it; and

3. When new information becomes available about the operation or pollutant management activities covered under this general permit that was not available at the time of general permit coverage.

Coverage under this general permit may be terminated as to an individual permittee for any of the reasons set forth above after appropriate notice and an opportunity for a hearing.

U. When an individual VPA permit may be requested. Any permittee operating under this general permit may request to be excluded from the coverage under this general permit by applying for an individual VPA permit. When an individual VPA permit is issued to a permittee the applicability of this general permit to the individual permittee is automatically terminated on the effective date of the individual VPA permit.

V. Civil and criminal liability Transfer of coverage under this general permit. Nothing in this permit shall be construed to relieve the permittee from civil and criminal penalties for noncompliance with the terms of this permit.

1. Permits are not transferable to any person except after notice to the department. The department may require modification or revocation and reissuance of this general permit to change the name of the permittee and to incorporate such other requirements as may be necessary. Except as provided in Part II V 2, coverage under this general permit may be transferred by the permittee to a new owner or operator only if the general permit has been modified to reflect the transfer or has been revoked and reissued to the new owner or operator.

2. As an alternative to transfers under Part II V 1, coverage under this general permit shall be automatically transferred to a new permittee if:

a. The current permittee notifies the department within 30 days of the transfer of the title to the facility or property;

b. The notice includes a written agreement between the existing and new permittees containing a specific date for transfer of general permit responsibility, coverage, and liability between them; and

c. The department does not within the 30-day time period, notify the existing permittee and the proposed new permittee of its intent to modify or revoke and reissue the coverage under this general permit. If the department notice is not received, the transfer is effective on the date specified in the agreement mentioned in Part II V 2 b.

W. Oil and hazardous substance liability Severability. Nothing in this permit shall be construed to preclude the institution of any legal action or relieve the permittee from any responsibilities, liabilities, or penalties to which the permittee is or may be subject under § 311 of the Clean Water Act or §§ 62.1-44.34:14 through 62.1-44.34:23 of the Code of Virginia.

X. Unauthorized discharge of pollutants. Except in compliance with this permit, it shall be unlawful for any permittee to:

1. Discharge into state waters sewage, industrial wastes, other wastes or any noxious or deleterious substances; or

2. Otherwise alter the physical, chemical or biological properties of such state waters and make them detrimental to the public health, or to animal or aquatic life, or to the uses of such waters for domestic or industrial consumption, or for recreation, or for other uses.

The provisions of this general permit are severable, and if any provision of this permit or the application of any provision of this general permit to any circumstance is held invalid, the application of such provision to other circumstances and the remainder of this general permit shall not be affected thereby.

Part III
Pollutant Management and Monitoring Requirements for Animal Waste End-Users

A. Pollutant management and monitoring requirements.

1. During the period beginning with the this general permit's effective date and lasting until the this general permit's expiration date, the permittee is authorized to manage pollutants at the location or locations identified in the registration statement and the facility's approved nutrient management plan written for the animal waste end-user.

2. At earthen liquid waste storage facilities constructed after December 1, 1998, to an elevation below the seasonal high water table or within one foot thereof, groundwater monitoring wells shall be installed. A minimum of one up gradient and one down gradient well shall be installed at each earthen waste storage facility that requires groundwater monitoring. Existing wells may be utilized to meet this requirement if properly located and constructed.

3. All facilities animal waste end-users previously covered under a general permit, individual VPA permit, or a VPDES permit that required groundwater monitoring shall continue monitoring consistent with the requirements listed below in this part regardless of where they the animal waste end-users are located relative to the seasonal high water table.

4. At facilities where Where groundwater monitoring is required, the following conditions apply:

a. One data set shall be collected from each well prior to any waste being placed in the storage facility.

b. The static water level shall be measured prior to bailing well water for sampling.

c. At least three well volumes of groundwater shall be withdrawn immediately prior to sampling each monitoring well.

5. In accordance with subdivisions 2 and 3 of this subsection, the groundwater shall be monitored by the permittee at the monitoring wells as specified below in Table 1 of Part III. Additional groundwater monitoring may be required in the facility's approved nutrient management plan written for the animal waste end-user.

6. If groundwater monitoring results for any monitored parameter demonstrate potential noncompliance with this general permit related to the waste storage facility, then the permittee shall submit an approvable groundwater monitoring action plan that outlines appropriate measures to be taken to address the noncompliance. The groundwater monitoring action plan shall be submitted to the department within 30 days of obtaining the monitoring results.

7. The analysis of the groundwater samples for ammonia nitrogen and nitrate nitrogen shall be performed by a laboratory accredited under the Virginia Environmental Laboratory Accreditation Program (VELAP) in accordance with 1VAC30-46-20. Field sampling, testing, and measurement of the static water level, pH, and conductivity where the sample is taken are not subject to the VELAP requirement.

TABLE 1

GROUNDWATER MONITORING

PARAMETERS

LIMITATIONS

UNITS

MONITORING REQUIREMENTS

Frequency

Sample Type

Static Water Level

NL

Ft

1/3 years

Measured

Ammonia Nitrogen

NL

mg/L

1/3 years

Grab

Nitrate Nitrogen

NL

mg/L

1/3 years

Grab

pH

NL

SU

1/3 years

Grab

Conductivity

NL

umhos/cm µmhos/cm

1/3 years

Grab

NL = No limit, this is a monitoring requirement only.

6. 8. Soil at the land application sites shall be monitored as specified below in Table 2 of Part III. Additional soils monitoring may be required in the facility's approved nutrient management plan written for the animal waste end-user.

TABLE 2

SOILS MONITORING

PARAMETERS

LIMITATIONS

UNITS

MONITORING REQUIREMENTS

Frequency

Sample Type

pH

NL

SU

1/3 years

Composite

Phosphorus

NL

ppm or lbs/ac

1/3 years

Composite

Potash

NL

ppm or lbs/ac

1/3 years

Composite

Calcium

NL

ppm or lbs/ac

1/3 years

Composite

Magnesium

NL

ppm or lbs/ac

1/3 years

Composite

NL = No limit, this is a monitoring requirement only.

SU = Standard Units

7. 9. Soil monitoring shall be conducted at a depth of between 0-6 inches, unless otherwise specified in the facility's approved nutrient management plan written for the animal waste end-user.

8. 10. Waste shall be monitored as specified below in Table 3 of Part III. Additional waste monitoring may be required in the facility's approved nutrient management plan written for the animal waste end-user.

TABLE 3

WASTE MONITORING

PARAMETERS

LIMITATIONS

UNITS

MONITORING REQUIREMENTS

Frequency

Sample Type

Total Kjeldahl Nitrogen

NL

*

1/year

Composite

Ammonia Nitrogen

NL

*

1/year

Composite

Total Phosphorus

NL

*

1/year

Composite

Total Potassium

NL

*

1/year

Composite

Calcium

NL

*

1/year

Composite

Magnesium

NL

*

1/year

Composite

Moisture Content

NL

%

1/year

Composite

NL = No limit, this is a monitoring requirement only.

*Parameters for waste may be reported as a percent, as lbs/ton or lbs/1000 gallons, or as ppm where appropriate.

9. 11. Analysis of soil and waste shall be according to methods specified in the facility's approved nutrient management plan written for the animal waste end-user.

10. 12. All monitoring data collected as required by this section and any additional monitoring shall be maintained on site for a period of five years and shall be made available to department personnel upon request.

B. Other Site design, storage, and operation requirements or special conditions.

1. Any liquid manure collection and storage facility shall be designed and operated to (i) prevent point source discharges of pollutants to state waters except in the case of a storm event greater than the 25-year, 24-hour storm and (ii) provide adequate waste storage capacity to accommodate periods when the ground is frozen or saturated, periods when land application of nutrients should not occur due to limited or nonexistent crop nutrient uptake, and periods when physical limitations prohibit the land application of waste.

2. Waste storage facilities constructed after December 1, 1998, shall not be located on a 100-year floodplain. For the purposes of determining the 100-year floodplain, a Federal Emergency Management Agency (FEMA) Flood Insurance Rate Map (FIRM), a FEMA Letter of Map Amendment (LOMA), or a FEMA Letter of Map Revision (LOMR) shall be used.

3. Earthen waste storage facilities constructed after December 1, 1998, shall include a properly designed and installed liner. Such liner shall be either a synthetic liner of at least 20 mils thickness or a compacted soil liner of at least one foot thickness with a maximum permeability rating of 0.0014 inches per hour. A Virginia licensed professional engineer or an employee of the Natural Resources Conservation Service of the U.S. Department of Agriculture with appropriate engineering approval authority shall certify that the siting, design, and construction of the waste storage facility comply with the requirements of this general permit. This certification shall be maintained on site.

4. At earthen waste storage facilities constructed below the seasonal high water table, the top surface of the waste must be maintained at a level of at least two feet above the water table.

5. All liquid waste storage or treatment facilities shall maintain at least one foot of freeboard at all times, up to and including a 25-year, 24-hour storm.

6. For new waste storage or treatment facilities constructed after November 16, 2014, the facilities shall be constructed, operated, and maintained in accordance with the applicable practice standard adopted by the Natural Resources Conservation Service of the U.S. Department of Agriculture and approved by the department. A Virginia licensed professional engineer or an employee of the Natural Resources Conservation Service of the U.S. Department of Agriculture with appropriate engineering approval authority shall certify that the siting, design, and construction of the waste storage facility comply with the requirements of this general permit. This certification shall be maintained on site.

7. The permittee shall notify the department's regional office at least 14 days prior to (i) animals being initially placed in the confined facility into confinement or (ii) the utilization of any new waste storage or treatment facilities.

8. Semi-solid and solid waste shall be stored in a manner that prevents contact with surface water and groundwater. Waste that is stockpiled outside for more than 14 days shall be kept in a waste storage facility or at a site that provides adequate storage. Adequate storage shall, at a minimum, include the following:

a. Waste shall be covered to protect it from precipitation and wind;

b. Stormwater shall not run onto or under the stored waste;

c. A minimum of two feet separation distance to the seasonal high water table or an impermeable barrier shall be used under the stored waste. All waste storage facilities that use an impermeable barrier shall maintain a minimum of one foot separation between the seasonal high water table and the impermeable barrier. "Seasonal high water table" means that portion of the soil profile where a color change has occurred in the soil as a result of saturated soil conditions or where soil concretions have formed. Typical colors are gray mottlings, solid gray, or black. The depth in the soil at which these conditions first occur is termed the seasonal high water table. Impermeable barriers shall be constructed of at least 12 inches of compacted clay, at least four inches of reinforced concrete, or another material of similar structural integrity that has a minimum permeability rating of 0.0014 inches per hour (1X10-6 centimeters per second); and

d. For waste that is not stored in a waste storage facility or under roof, the storage site must be at least 100 feet from any surface water, intermittent drainage, wells, sinkholes, rock outcrops, and springs. For semi-solid and solid waste that is stored on an impermeable barrier and where any stormwater runoff is collected in the waste storage facility, the semi-solid and solid waste can be stored adjacent to the waste storage facility regardless of the location of the waste storage facility so long as any surface water, intermittent drainage, wells, sinkholes, rock outcrops, and springs are protected from runoff from the stored semi-solid and solid waste.

Semi-solid and solid waste that is stored on an impermeable barrier and where any stormwater runoff is collected in a waste storage facility is considered adequate storage and is therefore not required to be covered.

9. All equipment needed for the proper operation of the permitted facilities shall be maintained in good working order. The manufacturer's operating and maintenance manuals shall be retained for references to allow for timely maintenance and prompt repair of equipment when appropriate. The permittee shall periodically inspect for leaks on equipment used for land application of waste.

10. All treated wastes generated by a digester or other manure treatment technologies shall be approved by the department and shall be managed by a facility the animal waste end-user covered under this general permit and in accordance with the following conditions:

a. All treated wastes generated by a digester or other manure treatment technologies must be managed through an approved nutrient management plan or transferred to another entity in accordance with animal waste transfer requirements in Part III B 15 C 6 and 16 7.

b. When a facility animal waste end-user covered under this general permit generates a treated waste from animal waste and other feedstock, the permittee shall maintain records related to the production of the treated waste.

(1) If off-site wastes are added to generate the treated waste, then the permittee shall record the following items:

(a) The amount of waste brought to the facility animal waste end-user; and

(b) From whom and where the waste originated.

(2) For all treated wastes generated by the facility animal waste end-user, the permittee shall record the following items:

(a) The amount of treated waste generated;

(b) The nutrient analysis of the treated waste; and

(c) The final use of the treated waste.

(3) Permittees shall maintain the records required by Part III B 10 b (1) and (2) on site for a period of three years. All records shall be made available to department personnel upon request.

11. When the waste storage facility is no longer needed, the permittee shall close it in a manner that (i) minimizes the need for further maintenance and (ii) controls, minimizes, or eliminates, to the extent necessary to protect human health and the environment, the postclosure escape of uncontrolled leachate, surface runoff, or waste decomposition products to the groundwater, surface water, or the atmosphere. Prior to closure, the permittee shall notify the department of any plans to close a liquid waste storage facility. At closure, the permittee shall remove all waste residue from the animal waste storage facility. Removed waste materials shall be utilized according to the approved NMP.

C. Animal waste use and transfer requirements.

11. 1. Animal waste generated by this facility an animal waste end-user that is subject to this general permit shall not be applied to fields owned by or under the operational control of either the permittee or a legal entity in which the permittee has an ownership interest unless the fields are included in the facility's approved nutrient management plan written for this animal waste end-user.

12. 2. The permittee shall implement a nutrient management plan (NMP) developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia and approved by the Department of Conservation and Recreation and maintain the plan on site. All revised and Department of Conservation and Recreation approved NMPs shall be submitted to the department prior to the expiration of the previous NMP. The NMP shall address the form, source, amount, timing, and method of application of nutrients on each field to achieve realistic production goals, while minimizing nitrogen and phosphorus loss to ground groundwaters and surface waters. The terms of the NMP shall be enforceable through this general permit. The NMP shall contain at a minimum the following information:

a. Site map indicating the location of the waste storage facilities and the fields where waste will be applied;

b. Site evaluation and assessment of soil types and potential productivities;

c. Nutrient management sampling including soil and waste monitoring;

d. Storage and land area requirements;

e. Calculation of waste application rates; and

f. Waste application schedules.

13. 3. Waste shall not be land applied within buffer zones. Buffer zones at waste application sites shall, at a minimum, be maintained as follows:

a. Distance from occupied dwellings not on the permittee's property: 200 feet (unless the occupant of the dwelling signs a waiver of the buffer zone);

b. Distance from water supply wells or springs: 100 feet;

c. Distance from surface water courses: 100 feet (without a permanent vegetated buffer) or 35 feet (if a permanent vegetated buffer exists). Other site-specific conservation practices may be approved by the department that will provide pollutant reductions equivalent or better than the reductions that would be achieved by the 100-foot buffer or 35-foot wide vegetated buffer;

d. Distance from rock outcropping (except limestone): 25 feet;

e. Distance from limestone outcroppings: 50 feet; and

f. Waste shall not be applied in such a matter that it would discharge to sinkholes that may exist in the area.

14. 4. The following land application records shall be maintained:

a. The identification of the land application field sites where the waste is utilized or stored;

b. The application rate;

c. The application dates; and

d. What crops have been planted.

These records shall be maintained on site for a period of five years after the date the application is made and shall be made available to department personnel upon request.

15. 5. In cases where a waste storage facility is threatened by emergencies such as fire or flood or where these conditions are imminent, animal waste can be land applied outside of the spreading schedule outlined in the NMP written for the animal waste end-user. If this occurs, then the animal waste end-user shall document the land application information in accordance with Part III C 4 and notify the department in accordance with Part II F 3.

6. Animal waste generated by this facility an animal waste end-user that is subject to this general permit may be transferred from the permittee to another person, if one or more of the following conditions are met:

a. Animal waste generated by this facility an animal waste end-user that is subject to this general permit may be transferred off-site for land application or another acceptable use approved by the department, if:

(1) The sites where the animal waste will be utilized are included in this permitted facility's the animal waste end-user's approved nutrient management plan; or

(2) The sites where the animal waste will be utilized are included in another permitted facility's entity's approved nutrient management plan.

b. Animal waste generated by this facility an animal waste end-user that is subject to this general permit may be transferred off-site without identifying in the permittee's approved nutrient management plan the fields where such waste will be utilized, if the following conditions are met:

(1) The animal waste is registered with the Virginia Department of Agriculture and Consumer Services in accordance with regulations adopted pursuant to subdivision A 2 of § 3.2-3607 A 2 of the Code of Virginia; or

(2) When the permittee transfers to another person more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) in any 365-day period, the permittee shall maintain records in accordance with Part III B 16 C 7.

16. 7. Animal waste may be transferred from a permittee to another person without identifying the fields where such waste will be utilized in the permittee's approved nutrient management plan if the following conditions are met:

a. When a permittee transfers to another person more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) in any 365-day period, the permittee shall provide that person with:

(1) Permittee's name, address, and the general permit number;

(2) A copy of the most recent nutrient analysis of the animal waste; and

(3) An animal waste fact sheet.

b. When a permittee transfers to another person more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) in any 365-day period, the permittee shall keep a record of the following:

(1) The recipient recipient's name and address;

(2) The amount of animal waste received by the person;

(3) The date of the transaction;

(4) The nutrient analysis of the animal waste;

(5) The locality in which the recipient intends to utilize the animal waste (i.e., nearest town or city and zip code);

(6) The name of the stream or waterbody, if known, to the recipient that is nearest to the animal waste utilization or storage site; and

(7) The signed waste transfer records form acknowledging the receipt of the following:

(a) The animal waste;

(b) The nutrient analysis of the animal waste; and

(c) An animal waste fact sheet.

c. Permittees shall maintain the records required by Part III B 16 C 7 a and b for at least three years after the date of the transaction and shall make them available to department personnel upon request.

17. When the waste storage or treatment facility is no longer needed, the permittee shall close it in a manner that (i) minimizes the need for further maintenance and (ii) controls, minimizes, or eliminates, to the extent necessary to protect human health and the environment, the postclosure escape of uncontrolled leachate, surface runoff, or waste decomposition products to the groundwater, surface water, or the atmosphere. At closure, the permittee shall remove all waste residue from the animal waste storage or treatment facility. Removed waste materials shall be utilized according to the approved NMP.

18. As required by § 62.1-44.17:1 F of the Code of Virginia, each D. Each permittee covered under this general permit shall have completed the training program offered or approved by the department in the two years prior to submitting the registration statement for general permit coverage or shall complete such training within one year after the registration statement has been submitted for general permit coverage. All permittees shall complete the training program at least once every three years.

9VAC25-192-80 Tracking and accounting requirements for animal waste end-users

A. When an animal waste end-user is the recipient of more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% percent or more moisture) in any 365-day period from an owner or operator of an animal feeding operation covered by a general permit, an individual VPA permit, or a VPDES permit, the end-user shall maintain records regarding the transfer and land application of animal waste.

1. The animal waste end-user shall provide the permittee with the following items:

a. End-user End-user's name and address;

b. The locality in which the end-user intends to utilize the waste (i.e., nearest town or city and zip code);

c. The name of the stream or waterbody, if known, to the end-user that is nearest to the waste utilization or storage site; and

d. Written acknowledgement acknowledgment of receipt of:

(1) The waste;

(2) The nutrient analysis of the waste; and

(3) An animal waste fact sheet.

2. The animal waste end-user shall record the following items regarding the waste transfer:

a. The source source's name, address, and permit number (if applicable);

b. The amount of animal waste that was received;

c. The date of the transaction;

d. The final use of the animal waste;

e. The locality in which the waste was utilized (i.e., nearest town or city and zip code); and

f. The name of the stream or waterbody, if known, to the recipient that is nearest to the waste utilization or storage site.

Records regarding animal waste transfers shall be maintained on site for a period of three years after the date of the transaction. All records shall be made available to department personnel upon request.

3. If waste is land applied, then the animal waste end-user shall keep a record of the following items regarding the land application of the waste:

a. The nutrient analysis of the waste;

b. Maps indicating the animal waste land application fields and storage sites;

c. The land application rate;

d. The land application dates;

e. What crops were planted;

f. Soil test results, if obtained;

g. NMP, if applicable; and

h. The method used to determine the land application rates (i.e., phosphorus crop removal, waste nutrient analysis rate, soil test recommendations, or a nutrient management plan).

Records regarding land application of animal waste shall be maintained on site for a period of three years after the date the application is made. All records shall be made available to department personnel upon request.

B. Any duly authorized agent of the board department may, at reasonable times and under reasonable circumstances, enter any establishment or upon any property, public or private, for the purpose of obtaining information or conducting surveys or investigations necessary in the enforcement of the provisions of this regulation.

9VAC25-192-90 Utilization and storage Storage and land application requirements for transferred animal waste

A. An animal waste end-user who receives animal waste from an owner or operator of an animal feeding operation covered by a general permit, an individual VPA permit, or a VPDES permit shall comply with the requirements outlined in this section.

B. Storage requirements. An animal waste end-user who receives animal waste from an owner or operator of an animal feeding operation covered by a general permit, an individual VPA permit, or a VPDES permit shall comply with the requirements outlined in this subsection regarding storage of animal waste in his the owner or operator's possession or under his the owner or operator's control.

1. Animal Semi-solid and solid waste shall be stored in a manner that prevents contact with surface water and groundwater. Animal Semi-solid and solid waste that is stockpiled outside for more than 14 days shall be kept in a waste storage facility or at a site that provides adequate storage. Adequate storage shall, at a minimum, include the following:

a. Animal Semi-solid and solid waste shall be covered to protect it from precipitation and wind;

b. Stormwater shall not run onto or under the stored animal semi-solid and solid waste;

c. A minimum of two feet separation distance to the seasonal high water table or an impermeable barrier shall be used under the stored waste. All waste storage facilities that use an impermeable barrier shall maintain a minimum of one foot separation between the seasonal high water table and the impermeable barrier. "Seasonal high water table" means that portion of the soil profile where a color change has occurred in the soil as a result of saturated soil conditions or where soil concretions have formed. Typical colors are gray mottlings, solid gray, or black. The depth in the soil at which these conditions first occur is termed the seasonal high water table. Impermeable barriers shall be constructed of at least 12 inches of compacted clay, at least four inches of reinforced concrete, or another material of similar structural integrity that has a minimum permeability rating of 0.0014 inches per hour (1X10-6 centimeters per second); and

d. For animal semi-solid and solid waste that is not stored in a waste storage facility or under roof, the storage site must be at least 100 feet from any surface water, intermittent drainage, wells, sinkholes, rock outcrops, and springs. For semi-solid and solid waste that is stored on an impermeable barrier and where any stormwater runoff is collected in the waste storage facility, the semi-solid and solid waste can be stored adjacent to the waste storage facility regardless of the location of the waste storage facility so long as surface water, intermittent drainage, wells, sinkholes, rock outcrops, and springs are protected from runoff from the stored semi-solid and solid waste.

Semi-solid and solid waste that is stored on an impermeable barrier and where any stormwater runoff is collected in a waste storage facility is considered adequate storage and is therefore not required to be covered.

2. Any liquid animal waste collection and storage facility shall be designed and operated to (i) prevent point source discharges of pollutants to state waters except in the case of a storm event greater than the 25-year, 24-hour storm and (ii) provide adequate waste storage capacity to accommodate periods when the ground is frozen or saturated, periods when land application of nutrients should not occur due to limited or nonexistent crop nutrient uptake, and periods when physical limitations prohibit the land application of waste.

3. Waste storage facilities constructed after December 1, 1998, shall not be located on a 100-year floodplain. For the purposes of determining the 100-year floodplain, a Federal Emergency Management Agency (FEMA) Flood Insurance Rate Map (FIRM), a FEMA Letter of Map Amendment (LOMA), or a FEMA Letter of Map Revision (LOMR) shall be used.

4. Earthen waste storage facilities constructed after December 1, 1998, shall include a properly designed and installed liner. Such liner shall be either a synthetic liner of at least 20 mils thickness or a compacted soil liner of at least one foot thickness with a maximum permeability rating of 0.0014 inches per hour. A Virginia licensed professional engineer or an employee of the Natural Resources Conservation Service of the U.S. Department of Agriculture with appropriate engineering approval authority shall certify that the siting, design, and construction of the waste storage facility comply with the requirements of this subsection. This certification shall be maintained on site.

5. At earthen waste storage facilities constructed below the seasonal high water table, the top surface of the waste must be maintained at a level of at least two feet above the water table.

6. All liquid waste storage or treatment facilities shall maintain at least one foot of freeboard at all times, up to and including a 25-year, 24-hour storm.

C. Land application requirements. An animal waste end-user who (i) receives more than 10 tons of solid or semi-solid animal waste (solid or semi-solid animal waste contains less than 85% moisture) or more than 6,000 gallons of liquid animal waste (liquid animal waste contains 85% or more moisture) from an owner or operator of an animal feeding operation covered by a general permit, an individual VPA permit, or VPDES permit and (ii) land applies animal waste shall follow appropriate land application requirements as outlined in this subsection. The application of animal waste shall be managed to minimize adverse water quality impacts.

1. The maximum application rates can be established by the following methods:

a. Phosphorus crop removal application rates can be used when:

(1) Soil test phosphorus levels do not exceed the values listed in the Phosphorus Environmental Thresholds table below:

Phosphorus Environmental Thresholds

Region

Soil Test P (ppm)
VPI & SU Soil Test (Mehlich I)*

Eastern Shore and Lower Coastal Plain

135

Middle and Upper Coastal Plain and Piedmont

136

Ridge and Valley

162

*If results are from another laboratory, then the Department of Conservation and Recreation approved conversion factors must be used.

(2) The phosphorus crop removal application rates are set forth by regulations promulgated by the Department of Conservation and Recreation in accordance with § 10.1-104.2 of the Code of Virginia.

b. Animal waste may be applied to any crop once every three years at a rate of no greater than 80 pounds of plant available phosphorus per acre when:

(1) The plant available phosphorus supplied by the animal waste is based on a waste nutrient analysis obtained in the last two years;

(2) In the absence of current soil sample analyses and recommendations; and

(3) Nutrients have not been supplied by an organic source, other than pastured animals, to the proposed land application sites within the previous three years of the proposed land application date of animal waste.

c. Soil test recommendations can be used when:

(1) Accompanied by analysis results for soil tests that have been obtained from the proposed field or fields in the last three years;

(2) The analytical results are from procedures in accordance with 4VAC50-85-140 A 2 f; and

(3) Nutrients from the waste application do not exceed the nitrogen or phosphorus recommendations for the proposed crop or double crops. The recommendations shall be in accordance with 4VAC50-85-140 A 2 a.

d. A nutrient management plan developed by a certified nutrient management planner in accordance with § 10.1-104.2 of the Code of Virginia.

2. The timing of land application of animal waste shall be appropriate for the crop, and in accordance with 4VAC50-85-140 A 4, except that no waste may be applied to ice covered or snow covered ground or to soils that are saturated.

3. Animal waste shall not be land applied within buffer zones. Buffer zones at waste application sites shall, at a minimum, be maintained as follows:

a. Distance from occupied dwellings: 200 feet (unless the occupant of the dwelling signs a waiver of the buffer zone);

b. Distance from water supply wells or springs: 100 feet;

c. Distance from surface water courses: 100 feet (without a permanent vegetated buffer) or 35 feet (if a permanent vegetated buffer exists). Other site-specific conservation practices may be approved by the department that will provide pollutant reductions equivalent or better than the reductions that would be achieved by the 100-foot buffer;

d. Distance from rock outcropping (except limestone): 25 feet;

e. Distance from limestone outcroppings: 50 feet; and

f. Waste shall not be applied in such a manner that it would discharge to sinkholes that may exist in the area.

4. In cases where the waste storage facility is threatened by emergencies such as fire or flood or where these conditions are imminent, animal waste can be land applied outside of the spreading schedule outlined in the animal waste fact sheet. If this occurs, then the animal waste end-user shall document the land application information in accordance with 9VAC25-192-80 A 3.

D. Animal waste end-users shall maintain the records demonstrating compliance with the requirements of subsections B and C of this section for at least three years and make them available to department personnel upon request.

E. The activities of the animal waste end-user shall not contravene the Water Quality Standards, as amended and adopted by the board, (9VAC25-260) or any provision of the State Water Control Law (§ 62.1-44 et seq. of the Code of Virginia).

F. Any duly authorized agent of the board department may, at reasonable times and under reasonable circumstances, enter any establishment or upon any property, public or private, for the purpose of obtaining information or conducting surveys or investigations necessary in the enforcement of the provisions of this regulation.

9VAC25-192-9998 FORMS (9VAC25-192)

Virginia DEQ Registration Statement for VPA General Permit for Animal Feeding Operations for Owners of Animal Feeding Operations, RS, VPG1 (rev. 3/14)

Virginia DEQ Registration Statement for VPA General Permit for Animal Feeding Operations for Animal Waste End-Users, RS End-Users, VPG1 (rev. 3/14)

Virginia DEQ Registration Statement for VPA General Permit for Animal Feeding Operations and Animal Waste Management for Owners of Animal Feeding Operations, RS AFO Owners, VPG1 (rev. 11/2024)

Virginia DEQ Registration Statement for VPA General Permit for Animal Feeding Operations and Animal Waste Management for Animal Waste End-Users, RS End-Users, VPG1 (rev. 11/2024)

Local Government Ordinance Form (eff. 11/94)

Virginia DEQ Fact Sheet for Animal Waste Use and Storage (rev. 4/14)

Virginia DEQ Fact Sheet for Animal Waste Use and Storage (rev. 11/2024)